AI infrastructure

Sharon AI's Sydney AI site nears December handover to ESDS with 8,208 chips installed

ESDS says the 8,208 NVIDIA B300 chips at Sharon AI's Sydney facility are installed and in final testing, with handover due in mid-December 2026 and billing planned from January 2027.

ESDS Software Solution announced on 21 November that the Sydney AI factory now has all 8,208 NVIDIA B300 chips in place, and that the system has entered final testing. The hardware and the data-centre capacity belong to Sharon AI, an Australia-based company. ESDS expects to take handover from Sharon AI in mid-December 2026 and to begin charging customers in January 2027.

ESDS resells access to the capacity and operates the platform, packaging model training with round-the-clock network and security operations in one customer contract. According to ESDS, the customer agreements take in the whole facility, and their duration and exit conditions mirror its deal with Sharon AI. Customers have reserved all of the computing power for work such as training AI models, and they are charged for it even if they use less.

ESDS projects monthly customer billing of about US$30 million. Its monthly payment to Sharon AI is about US$21 million, set as a fixed rate per chip per hour. The gap of about US$9 million a month is before operating costs and tax. ESDS estimates monthly profit after tax of US$4 million to US$5 million, equal to 14% to 17% of revenue. Multibagg AI reported the company had earlier aimed for a margin of 14% to 18%.

In its financial clarification, ESDS put its commitment to Sharon AI at about US$1.26 billion over 60 months. Multibagg AI's earlier installation coverage valued the agreement at about US$1.25 billion, with an initial five-year term and an option to extend by two years.

ESDS says it funded a US$140 million cash deposit to Sharon AI in May 2026 from an advance paid by customers. The deposit will be offset against fees over the life of the contract, and it is refundable if Sharon AI does not deliver. ESDS says the deposit meets the requirement for a letter of credit or bank guarantee.

The December timing replaces an earlier October go-live target and matches the schedule Sharon AI published with its 16 November results. ESDS says it agreed the revised timetable with Sharon AI and informed customers. It intends to complete testing of the whole system before accepting handover, the point at which payment obligations begin for both sides. Customer testing is due to follow handover, and ESDS says it will tell the exchange when the facility is live.