NEXTDC lifts FY27 earnings guidance a month after M3 Melbourne power delay

NEXTDC has lifted its FY27 underlying EBITDA guidance to $260 million to $275 million and raised the floor of its net revenue range. The outlook still leaves out the affected M3 Melbourne contracts and sits well under the August forecast.

NEXTDC has narrowed upward its FY27 underlying EBITDA guidance to $260 million to $275 million, from the $245 million to $265 million it set on 21 October. The mid-point rises by $12.5 million, a month after a power delay at the M3 Melbourne campus prompted a deep downgrade and a share price slump.

The bottom of the net revenue range moves up by $10 million to $485 million, while the top stays at $500 million. Capital expenditure guidance holds at $4.5 billion to $5 billion. The company attributes the higher revenue floor to strong sales and growth outside the affected M3 contracts, plus more confidence about when customers will be delivered capacity.

In a statement released ahead of its annual general meeting, NEXTDC said the revised outlook continues to leave out revenue and attributable EBITDA from the M3 contracts concerned. That covers capacity already billing as well as any service level credits that may be payable. The company said it "cannot yet reliably estimate the FY27 contribution of those contracts and will update the market when it can."

Those M3 contracts accounted for about $140 million each of net revenue and underlying EBITDA in the guidance NEXTDC issued on 27 August. Business News Australia reported that the new range remains well short of the August forecast of $615 million to $640 million in net revenue and $385 million to $410 million in underlying EBITDA, with the EBITDA mid-point about a third lower.

The delay's effect on the company's property portfolio has not yet been quantified. Investment properties including M3 and S4 Sydney were carried at a combined $3.24 billion at 30 June, based on CBRE valuations, and NEXTDC said revised timing and cost to finish M3 are likely to change that figure. It expects the hit to appear in results for the half year to 31 December 2026 and intends to commission an outside valuation while preparing them.

Guidance is struck before any fair value movement on investment property. Underlying EBITDA also excludes one-off costs linked to the M3 delay and to dealing with what the company describes as "unsolicited corporate event activity".