Melbourne has passed Johor as the Asia Pacific market with the most data centre capacity taken up in 2026, datacenterHawk reported, and grid limits and community concerns are expected to steer new projects into regional Australia.

Melbourne now leads Asia Pacific on data centre absorption, with 1,546MW taken up so far in 2026, datacenterHawk said in its 3Q 2026 APAC Data Center Market Report. Johor ranked second on 1,279MW, followed by Jakarta on 973MW and Sydney on 710MW. Hyperscalers are committing to bigger campuses in Melbourne's west and competing harder for electricity.

Donny Gunadi, a senior insight analyst for APAC, said hyperscalers have continued to expand next to their existing sites in the west of the city. Gunadi said long waits for power infrastructure and energisation mean every customer must queue, and he said the operators who get power will be the ones who commit early, as he put it, "The ones who secure power will be those willing to commit early and lock in their place in the queue". Sydney's established precincts, by contrast, have tighter grid capacity and dearer land, which Gunadi said has pushed demand south.

Pre-committed capacity should keep Melbourne in front in the near term, although the gap to Sydney could close as power constraints ease. Melbourne hyperscale rates rose 32 per cent from 2025 to 2026, against 16 per cent in Sydney. That puts Melbourne alongside Seoul, Osaka, Tokyo and Singapore as one of the quickest-rising hyperscale markets in the region.

Across APAC, the report counted 18.6GW of commissioned colocation power that is built or preleased, while vacancy dropped to 2.96 per cent from 7.3 per cent a year earlier. It found 94 per cent of 2026 leasing in the region was preleased. Gunadi said Australian capacity is generally built only against firm customer commitments, and added: "We are not seeing signs of speculative over-ordering in Australia". He called AI a major driver, with most newly committed capacity designed for GPU workloads and liquid cooling, though he said it is hard to separate from ordinary cloud demand.

Gunadi said climbing prices could threaten Australia's AI ambitions. Building costs keep rising, and customers expect facilities to meet the standards set by major Western cloud, hyperscale and AI operators. In his view, sovereign and latency-sensitive services that must remain onshore will accept higher costs, but more portable work such as model training could relocate if the price gap with other markets grows too wide.

Gunadi expects regional Victoria and regional NSW to feature strongly in Australian development during 2027. Projects he pointed to include CDC's proposed campus near Wagga Wagga, IREN's planned campus at Bundey in South Australia and Keppel's campus at Morwell in Victoria. He said "social licence and community expectations are getting more attention" and expects 2027 to be a year of adjustment.

Beyond Sydney and Melbourne, Gunadi named Western Australia, South Australia, Queensland and the Northern Territory as emerging contenders for large new capacity. He cited Queensland's Western Downs Digital Park and South Australia's data centre strategy as signs of state government backing, and noted CDC is also planning a campus at Maddington. Governments increasingly want data centres to supply more of their own power and lean less on the grid, he said, which suits sites near new renewable generation and transmission.