AEMO interim guide sets 30 MW line for large inverter-based loads such as data centres
AEMO's interim guide, dated 19 November 2026, treats inverter-based loads of 30 MW or more as large and calls for a detailed site model at least six months before energisation. Feedback closes on 17 December 2026.
AEMO has released an interim guide on connecting inverter-based loads, data centres among them, with an effective date of 19 November 2026. Under the guide, a load is large once its nameplate reaches 30 MW, and where a single connection agreement spans several items of plant, the nameplate is the sum of what they consume. The guide is built on the Package 2 final rule that the AEMC issued on 12 November 2026.
Operators of large loads are to supply a detailed site-specific model at least six months ahead of energisation, and a footnote notes that some networks may ask for it sooner. For smaller loads, the model is supplied when the network asks. A companion FAQ says inverter-based loads above 10 MW already fall inside the under-frequency load-shedding scheme, under clause S5.3.10.
The FAQ also sets out how batteries and solar are handled on a data centre site. A UPS that maintains supply and is not designed to export through the connection point is grouped with the load, and it is not registered as a bi-directional unit. A further battery outside that UPS, controllable by itself, counts as separate plant, while solar on the site is listed as asynchronous generation. Backup plant that never operates in parallel with the grid stays off the generation register, but plant that does run in parallel faces a registration path or an exemption application. The FAQ describes this approach as interim while a registration guide is reviewed.
AEMC chair Anna Collyer said the rules follow the principle that "once a customer is big enough to materially affect the grid, it must be treated as part of that grid". The AEMC rule requires large inverter-based loads to stay connected through disturbances, and obliges network businesses to weigh the combined effect of large loads nearby. The AEMC cited a July 2024 event in Virginia, where 1,500 MW disconnected at once. It also pointed to forecast data centre demand rising from 5 to 34 terawatt-hours by 2035.
RenewEconomy reported that Fluence regards batteries as among the quickest routes to compliance. Fluence Energy senior manager of policy and strategy Sam Markham said storage can no longer be added later, since grid-support technology has to be active, modelled and compliant from day one. That view comes from the interview; the guide does not name Fluence or present a battery as the route through the standard. The guide gives no dollar price and no battery kilowatt-hours.
On timing, the consultation page shows submissions closing on 17 December 2026, a webinar on 2 December at 2:00pm AEST and an update in early 2027. The guide's own table puts the update on 29 January 2027 and says the date may change. An indicative timeline in a November fact sheet from the market bodies shows 27 Nov for the guide, whereas the guide and consultation page show 19 November. According to RenewEconomy, the AEMC rule applies immediately, with a 6-month grace period letting applicants well advanced in connection talks finish on the old access standards. That grace period is separate from the guide's six-month model requirement.