Lambruk plans 350 MW Mulwala data centre, but grid has room for stage 1 only

A locally backed developer wants to build a three-stage data centre campus next to Essential Energy's Mulwala substation in NSW. The proponent says the network can serve only the first stage, and the site still needs rezoning and state approval.

Lambruk Mulwala Futures, a company backed by local landholders and domestic investors, is proposing a data centre campus in three stages at Mulwala, New South Wales, with a grid draw of up to 350 MW. The Riverine Herald reported a cost of $4-8 billion and said the site sits roughly 2 km north of the town, on farmland belonging to Douglas Thomas. The Border Mail, which ran the story on the same day, said the advisory firm Lecroma handles planning and community consultation. No development partner has been named; the proponent intends to find one later to build and run the data halls.

The proponent distinguishes the connection limit from the computing load: the halls and associated plant could together pull 350 MW, while the computers themselves would take around 250 MW to 280 MW and the balance would go to cooling and other equipment. The land lies about 390 m from Essential Energy's Mulwala 132 kV zone substation, and the proponent says the utility has told it the network can support stage 1 only. Stages 2 and 3 depend on connection studies and any network upgrades.

Transgrid's 2026 Transmission Annual Planning Report, as covered by W.Media, puts NSW data centre connection enquiries above 20 GW. Transgrid said Sydney's capacity is largely committed and directed developers towards regional NSW, naming the Hunter and the Riverina, while cautioning that capacity is indicative and varies by project. It projects state data centre peak demand growing from about 660 MW in 2027 to 3.67 GW in 2036. The Border Mail added that AEMO's 2026 Electricity Statement of Opportunities has data centres using about 13 per cent of electricity supplied across the National Electricity Market by 2035-36, from roughly 3 per cent at present.

The proponent points to the NSW Data Centre Guidelines, under which facilities must lower grid demand by a quarter of average load for up to two hours during grid stress, without using diesel. Its response would be batteries plus computing load that can be flexed.

The overall holding is about 168 ha, of which the campus would take about 62 ha, the existing Mulwala Solar Farm would keep about 61 ha and about 27 ha is earmarked for future industry. The solar farm has built about 31 MW of its approved 80 MW. Cooling would use a closed loop filled once from the landowner's bore, so town water would not be drawn on.

Nothing has been approved and no planning document has been lodged. The proponent says existing zoning prohibits a data centre, so the planning rules would have to change. It intends to use the State Significant Development pathway, targeting a scoping report in December 2026, an environmental impact statement in March to April 2027 and public exhibition in mid-2027. The cost range comes solely from the Riverine Herald, which said it had contacted Federation Council for comment. No tenant is named, and no connection agreement exists for stages 2 and 3.