IREN details 900MW Wagga campus, but Transgrid capacity not yet secured

IREN's scoping report for the Redbank data centre near Wagga Wagga sets out a 900MW connection to Transgrid's 330kV substation, but no signed connection agreement or capacity allocation has been identified.

IREN has outlined a proposed data centre campus near Wagga Wagga in regional New South Wales that would need up to 900MW of gross electrical capacity, while the availability of transmission capacity remains subject to the connection process. The Redbank Data Centre would serve roughly 600MW of IT load. A scoping report prepared for IREN subsidiary TAS 1 Holdings places the site at Rowan, beside the Gregadoo Waste Management Centre, around 2.5km from Transgrid's existing 330kV substation.

For the connection, the report envisages three additional 330kV feeder bays at the Wagga Wagga substation, plus three buried cable circuits that would run mostly along Boiling Down Road to a new bulk substation on the site. That on-site facility would step voltage from 330kV to 132kV using four 375MVA transformers, and four further 132/33kV substations would supply the five data halls. IREN says it will pay for the dedicated connection assets, while the final design and any wider network upgrades will be settled with Transgrid through the formal connection process.

The scoping report says planning with Transgrid has run since May 2026, based on a 900MW connection. Asked about Redbank by W.Media, Transgrid said confidentiality requirements under the National Electricity Rules stopped it disclosing details of individual connection enquiries or applications. It pointed to its 2026 Transmission Annual Planning Report, which shows indicative capacity in regional NSW including Wagga Wagga, and said opportunities would depend on each application's scope. Under Transgrid's Network Capacity Allocation Policy, a large-load project gets provisional capacity once a Network Connection Agreement is signed, and the allocation becomes final only if readiness criteria are met within three months. The criteria cover permits, construction contracts, land, long-lead equipment and financing, and the proponent must have a complete application accepted by Transgrid. The scoping report identifies no signed agreement or formal allocation, and IREN previously said Redbank was outside its announced 5GW secured-power portfolio.

The 900MW figure is the peak gross requirement rather than expected average use. Using a design annualised power usage effectiveness of about 1.3, the report puts average facility demand at full IT load near 780MW.

IREN proposes staged delivery over about six to eight years, with a first 75MW gross block targeted for 2029 and similar blocks at six-month intervals, reaching 900MW by 2035. The design includes about 444 standby diesel generators, which IREN says would not run continuously, and closed-loop direct-to-chip cooling. Annual cooling make-up water is expected to be about 1 per cent of system volume, though the final volume is yet to be determined.

Planning is at an early stage. The NSW Planning Portal lists the project as a State Significant Development at the stage of preparing Secretary's Environmental Assessment Requirements, and it includes a change to the Wagga Wagga Local Environmental Plan for what is currently rural land. IREN's report anticipates a construction workforce of up to about 1,100 and more than 200 full-time equivalent operational roles at full capacity.

The Nightly reported that Wagga Wagga City Council finalised a policy on 16 November to seek 1.5 per cent of estimated capital costs for community funds. The Nightly said IREN did not respond to a request for comment and has not signalled agreement, and that the final approval decision rests with the NSW Government.

Redbank is separate from IREN's planned 800MW Bundey development in South Australia, for which a transmission connection agreement has been announced. It also sits close to CDC Data Centres' planned Gregadoo development of up to 1.4GW, and the two together would represent a potential 2.3GW of demand, both subject to planning and connection processes.