Data Centres Australia forecasts 3.9GW of capacity by 2030, up from 1.6GW

A new Data Centres Australia and DC Byte report lifts its 2030 capacity forecast to 3.9GW from 3.2GW. Melbourne's pipeline has overtaken Sydney's, and projects outside the two hubs hold a bigger share.

Data Centres Australia has lifted its capacity forecast for the Australian market in 2030 to 3.9GW, from an earlier 3.2GW, and expects 97 more facilities by then. The report was compiled with market intelligence firm DC Byte. It counts 163 operating data centres with combined capacity of 1.6GW.

Compared with the previous edition, forecast pipeline capacity is up by 5.2GW and capacity under construction has doubled. Construction growth is split evenly between Sydney and Melbourne, but activity at earlier stages has moved in different directions. In Melbourne, 1.2GW advanced from early stage to committed, against 0.7GW in Sydney.

Sydney's overall pipeline shrank by 3.6GW and its early stage capacity by 4.4GW, a drop the report attributes to energy constraints, approval timelines and recent policy changes. Melbourne's pipeline grew by 1.7GW and is now larger than Sydney's. Its early stage capacity grew by just 0.3GW, which suggests the gain came mostly from projects progressing rather than a flood of new proposals.

The report says Victoria's gains may reflect quicker approvals under the state government's Development Facilitation Program, while New South Wales projects go through the State Significant Development process with a less certain timetable. Data Centres Australia chief executive Belinda Dennett said Victoria's pipeline had grown sharply over six months, "likely attributable to the state government's efforts to attract investment". She said recent policy changes may affect whether that continues.

Two years ago, 19% of the total pipeline lay outside Sydney and Melbourne; the share is now 31%. Early stage proposals in Queensland, Tasmania, South Australia and Western Australia are part of that shift. Dennett said she expected the trend to continue as AI and neocloud workloads bring "different siting requirements".

Unlike counts built mainly on announcements or grid connection applications, DC Byte's method weighs viability, trying to separate likelier projects from speculative ones. Dennett said the report was designed to help "cut through the noise by qualifying project viability". Cloud and AI compute demand is named as a central driver of the expected growth.