671 of 759 submissions oppose AirTrunk's Kurri Kurri data centre

Exhibition of AirTrunk's proposed Kurri Kurri data centre ended on 11 November 2026 with 671 of 759 public submissions against it. Agency letters since posted show Cessnock council objecting and Ausgrid stating that grid connection is not yet approved.

Public exhibition of AirTrunk's proposed data centre at Loxford, near Kurri Kurri in New South Wales, ended on Wednesday 11 November, with 671 of 759 submissions opposing it, according to the Newcastle Herald and Newcastle Weekly. The Herald reported 77 submissions in support of the $3.7 billion proposal and 11 that offered comment. Cessnock City Council's own objection is counted among the 671.

The Connection Point went through the register's entries and found the submitters are largely local, with Kurri Kurri the most common suburb at 148 submissions, then Weston at 81. Its word search of the objections found references to electricity, power, energy or the grid in 405, noise in 389, water in 281 and fire in 138. Residents group RADIKKAL says 82 per cent of respondents to AirTrunk's own community survey did not want the project.

The project is an AI training facility on the former Hydro Aluminium smelter site, with an average load of 458.1 MW at full capacity, while the two outlets describe a 540-megawatt facility on Hart Road. The environmental impact statement proposes a dual overhead connection from the existing Ausgrid 132 kV line at the site boundary, and no augmentation of the transmission network. Ausgrid's letter of 11 November confirms formal connection talks with the proponent are under way, and lists detailed design, network impact assessments, easements, commercial arrangements and any augmentation as unresolved. The utility states that its letter is neither connection approval nor confirmation that network capacity is available. The Connection Point noted that Transgrid, which operates the transmission network above Ausgrid's, is not among the six agencies whose letters were posted.

Cessnock council's submission carries its 21 October resolution to object formally, and seeks a national moratorium on data centre approvals until federal frameworks are in place, to be requested from the federal Assistant Minister for Science, Technology and the Digital Economy. The council argues the impact statement does not adequately explain regional network implications, cumulative effects or energy security risks, and it asks how the figure of 254 full-time jobs was reached. AirTrunk claims more than 350 ongoing jobs, according to Newcastle Weekly. The council says any planning agreement will be worth not less than $46,118,317.50 including GST, which The Connection Point calculated amounts to the same 1 per cent contribution as the draft offer.

Hunter Water said the design, with 312 dry air-cooled chillers and potable use of 2.80 ML a year, does not pose a significant water security risk, and that its advice depends on that fact. It wants any shift to using water for cooling assessed as a formal modification. The EPA said an environment protection licence does not appear necessary, but asked how the project relates to the neighbouring Kurri Kurri Power Station. Fire and Rescue NSW recommends a fire safety study before construction. The Development Coordination Authority asked for part of the biodiversity mapping to be redone.

RADIKKAL spokesperson Graeme Davies said residents had given AirTrunk the same answer throughout, adding: "The minister now has 671 reasons to refuse it," he said. The group has asked the department to refer the application to the Independent Planning Commission, order an independent low-frequency noise study and recommend refusal. Supporters pointed to jobs and the site's industrial history, and the Hunter Region Business Enterprise Centre backed the project on condition of enforceable measures to cut town water use.

Because it is a State Significant Development, the decision rests with the NSW Government. The department has asked AirTrunk for a submissions report within two months of 12 November, about 12 January 2027.