Today's briefing

Friday 30 October 2026

  • NextDC shares have fallen 42 per cent after power delays at its M3 Melbourne data centre forced a deep guidance cut, and Grafa reports it now faces removal from the S&P/ASX 50 Index.
  • Elsewhere in data centres, EdgeConneX entered Australia in a 50-50 venture with Stockland, with 450MW of power secured, and coNEXA will spend $250 million on recycled water for NextDC's S4 Sydney.
  • In regulation, ACMA's maximum telco code penalty is set to rise from $250,000 to $10 million.

Data centres

NextDC faces ASX 50 demotion after 42% share plunge over Melbourne power delay

NextDC shares fell 42% after delays to power works at its M3 Melbourne data centre forced a deep guidance cut, and Grafa reports the company now faces removal from the S&P/ASX 50 Index.

Read the story →

Policy & regulation

2 stories

ACMA gets direct code enforcement and a $10 million penalty ceiling for telcos

Reforms outlined on 15 October 2026 let ACMA act on breaches of registered telco codes without a prior compliance order, with the maximum penalty rising from $250,000 to $10 million, according to ACCAN. A registration scheme could also bar providers with serious compliance failures from the market.

2 sources · 2 min read

Gosnells backs tighter data centre planning rules near homes

The City of Gosnells in Perth voted unanimously on 13 October to advance a planning scheme amendment and draft policy for data centres. They would be a discretionary use on General Industry land, with noise, water and power tests. CDC's Maddington facility is exempt.

1 source · 2 min read

Also today

4 stories

AI infrastructure

CoreWeave plans petabit-scale backbone with new PoP in Australia

CoreWeave announced on 27 October 2026 a wider Global AI Network built as a petabit-scale backbone, with new points of presence in seven markets including Australia. Work starts in the fourth quarter of 2026, with a full intercontinental loop targeted for mid-2027.

1 source · 1 min read