Firmus weighs US$1.5 billion bond as part of smaller debt package after IPO shelved
Nvidia-backed Firmus Grid is considering a bond of around US$1.5 billion within a debt package of up to about US$4 billion, according to people familiar with the matter. The Business Times, citing Bloomberg, reported the plan after the company dropped its IPO in October.
Australian AI infrastructure company Firmus Grid is considering a bond offering of around US$1.5 billion as part of a larger debt financing, according to people familiar with the matter cited by The Business Times in a Bloomberg report on Monday 23 November 2026. The move follows the company's decision in October to shelve its plans for an initial public offering.
The people said Firmus held talks as recently as the week before the report with banks and investors about a senior and mezzanine package totalling as much as around US$4 billion. That would be significantly smaller than the roughly US$7.5 billion package the company targeted two months earlier. The abandoned IPO had sought to raise as much as US$5.5 billion, including a greenshoe option. Firmus could try to issue the bond by the end of 2026, though timing and other details may change with market conditions, the people said.
Proceeds would mainly fund purchases of Nvidia's latest GB300 chips for an Indonesian data centre being developed by Firmus and DayOne Data Centers. According to the people, a separate bank loan is also under discussion, and both it and the bond would run for 69 months and form the senior portion of the package. The people said the bond yield could be around 8 per cent, while the loan margin could be about 325 basis points over the Secured Overnight Financing Rate. Firmus has obtained BBB investment-grade ratings from at least two international rating firms for the proposed bond, and the two instruments are expected to rank pari passu. Morgan Stanley is leading the financing and Firmus is inviting banks to join the underwriting group.
Firmus declined to discuss the talks, saying it does not comment on market speculation. The company said, "Funding arrangements and any details will be announced at the appropriate time". Morgan Stanley declined to comment.
Bloomberg described the fundraising as coming at a volatile time for the AI sector, with investors wary of high valuations and elevated global borrowing costs, and with the US stepping up scrutiny of where advanced chips end up. Nvidia, a Firmus backer, also faces fallout after chief executive Jensen Huang left earlier in November, and Moody's Ratings lowered its outlook on Nvidia to stable from positive in the week before the report, citing governance concerns.
Firmus began as a Bitcoin mining operation in Australia in 2019 and has secured US$2 billion in commitments from investors including Nvidia and Blackstone. It plans to build data centres it calls AI factories on Nvidia hardware, and investor documents seen by Bloomberg show a pipeline of 912 MW, of which 46 MW has been built.