Data centre cancellations put A$59bn of Australian financing under scrutiny
Five Australian data centre projects have been paused or scrapped in recent weeks, IFR reported, prompting lenders to place more value on power certainty and execution as the sector sits on A$59bn of debt and equity raised since 2025.
A run of delays and cancellations to Australian data centre projects is drawing attention to the A$59bn (US$40bn) of debt and equity financing raised for the sector since 2025, IFR reported on 20 November 2026. Quantum DC paused plans on 12 November for a 1.2GW hyperscale data centre near Adelaide, the fifth project disrupted in recent weeks. The proposed Tungkillo Compute and Energy Hub was suspended after concerns about water and energy use, its location and its effect on farmland.
NEXTDC earlier this month suspended work on its M3 data centre expansion in Melbourne because of power delays and community backlash. Stockland abandoned a proposed A$1.2bn data centre at Kogarah in Sydney, and AirTrunk this month scrapped a proposed 140MW facility at Lane Cove, after Goodman Group dropped a A$1.2bn plan in the same suburb in September. A banker told IFR the Kogarah and Lane Cove sites were too close to homes, with a community perception that they were not large enough.
Belinda Dennett, chief executive of trade group Data Centres Australia, said delays in planning approvals and electricity infrastructure could weaken Australia's appeal to investors. She said, "Capital is mobile and customers and investors have choice."
Andrew Jones, associate portfolio manager at Realm Investments, said there was a raised focus on project execution risk, with attention shifting to location, electricity access and customer contracts. He described NEXTDC's M3 as unique because it sits in a residential area rather than an industrial one. Lucinda Jerogin, associate economist at Commonwealth Bank of Australia, said "energy is the most acute constraint, while community opposition and social licence are also among the main risks, although the buildout would remain significant even after accounting for projects that might not proceed".
RenewMap counts around 126 projects under construction or in development, though most proposed capacity lacks planning approval. CBA estimates only about 7GW of a 23GW announced pipeline is likely to be delivered over the coming decade. The Reserve Bank of Australia data show A$35bn raised by early September this year, against A$24bn in 2025, with debt making up 85 per cent of new funding.
Lenders are putting more value on power certainty and execution, which could lift loan pricing. A Sydney-based banker said assumptions behind low margins were being heavily tested, but median spreads of 185bp are only 10bp above those for other corporate borrowers, suggesting competition for deals continues. Lenders are expected to distinguish between established hyperscalers and AI-focused facilities with shorter contracts, quickly depreciating equipment and less-established counterparties.
In late October, Blackstone-backed AirTrunk closed a A$4.25bn three-year green loan for its SYD3 campus in Western Sydney, drawing 32 institutions and pricing at 252bp all-in. Blue Owl-backed Stack Infrastructure launched an A$8.585bn five-year green loan for a Melbourne campus, with a margin of 250bp over BBSY during construction. The banker said both reflect long-term contracts with hyperscalers and sites in industrial locations.