coNEXA commits $250m to recycled water supply for NEXTDC's S4 Sydney data centre
coNEXA Infrastructure Partners is spending more than $250 million to extend its AquaNet network to NEXTDC's Horsley Park site, with construction due to start in November 2026 and first water expected in late 2027.
coNEXA Infrastructure Partners will pipe recycled water to NEXTDC's S4 Sydney data centre at Horsley Park, backing the work with more than $250 million through its AquaNet business. Law firm Piper Alderman, which advised coNEXA on development and financing, said the privately funded project is believed to be Australia's largest recycled water connection to a data centre.
Supply will come from coNEXA's Fairfield recycled water plant, which will send an additional 16 million litres a day, giving the site an option other than drinking water for cooling. Piper Alderman said the scheme would put up to 5.8 billion litres of treated wastewater a year to use instead of sending it to the ocean. It also said the scheme would take pressure off a constrained sewerage network by removing flows matching the output of up to 35,000 homes.
AquaNet has served Western Sydney businesses and industry since 2011. NEXTDC is the anchor customer for the extension, which is designed to let other data centres, industry and councils join later. S4 Sydney is planned for up to 365MW of IT capacity and a power usage effectiveness of 1.125 at full IT load.
Piper Alderman said NSW data centre approvals increasingly refer to recycled water for cooling, yet little infrastructure exists to deliver it at scale. The firm said there was no market template for a privately funded, licensed recycled water network serving a hyperscale customer. coNEXA needed terms that lenders would accept for its first anchor customer while keeping room to add users and later move to multi-user project financing.
Piper Alderman's work spanned a long-term supply agreement with NEXTDC, two design and construct contracts for the pipeline, pump station and reservoir, and land and easement purchases. It also covered approvals under the Water Industry Competition Act 2006 (NSW), arrangements with Sydney Water to draw wastewater from the sewer network, and Foreign Investment Review Board and ACCC matters.
The project has won IPART approval and secured senior secured financing. Construction is scheduled to start in November 2026, with first water expected in late 2027.
NEXTDC's Chief Engineering and Design Officer Jeff Van Zetten said, "S4 Sydney is designed to be world leading on energy efficiency, and recycled water is part of how we get there." coNEXA Chief Executive Officer Kurt Dahl said NEXTDC's commitment "unlocks the scale and demand to build the first stage of a network that will serve more of Western Sydney industry and the community over time." NSW Minister for Water Rose Jackson described the project as "exactly the type of project we envisioned when we released the NSW Data Centre Guidelines."