Tuesday 24 November 2026 · Vol. 1 · No. 024 SearchSign inSubscribe
Best Effort

The weekday briefing on Australian telecommunications, data centres and AI infrastructure.

Carriers & networks

Vector Fibre recovery continues after Auckland CBD fire damaged basement fibre

Vector Fibre crews completed 11 planned cable batches of splicing and rerouting on Sunday 22 November 2026, as recovery from a Fanshawe Street fire in Auckland's CBD moves into a third day. Upstream carrier links are restored, but some dark fibre, DWDM and Vector circuits remain affected.

Vector Fibre field teams completed 11 planned cable batches of fibre splicing and rerouting on Sunday 22 November 2026, as the multi-day recovery from an Auckland CBD building fire continued. Vector said the run rate improved as work progressed, helped by splice-location preparation done earlier and an additional field team working in parallel. Field teams stood down on Sunday evening, while engineering and network teams planned further restoration batches for Monday.

The incident began on Friday 20 November 2026, when a well-involved fire broke out at a Fanshawe Street building housing Vector Fibre infrastructure. Emergency services cordoned off the area. The status page, which appears to be run by an operator whose own network was affected, reported impacts to some Vector circuits, dark fibre customer services delivered over Vector Fibre, core network links and upstream carrier paths. That operator rerouted core traffic over alternative paths where it could and warned of path changes and differences in latency or performance.

By early afternoon on Friday the basement fire had been extinguished, but the site remained under FENZ control and Vector could not assess the damage, so no estimated restoration time was available. Access was granted that evening, and an initial assessment found extensive damage to fibre infrastructure through the basement, along with the loss of both generator and UPS services. Building access stayed restricted to accompanied assessment, and structural clearance for permanent restoration work was outstanding. Vector warned that losing backup power raised the risk of further impacts, including to services that had stayed up.

On Saturday 21 November, Vector said it had seen the anticipated extra service impacts after UPS battery capacity ran out and the site generator was taken offline. It said it was talking to the site controllers about whether the generator could safely return to service.

The restoration strategy is to build alternative fibre routes that bypass the affected site. Splicing and restoration work ran around the clock from Saturday, with the first batch expected to be low volume while teams proved the end-to-end process. By Saturday evening a small number of customer services had been restored, which Vector said was consistent with its expectations. Field teams worked until about 01:00 on Sunday and resumed between 08:30 and 09:00.

At 3:07 PM NZDT on Sunday, the status page reported that links to previously disrupted upstream carriers were restored and upstream capacity to those carriers was back to normal. Some customer dark fibre, DWDM and Vector circuits were still affected, along with reduced resiliency on some core network links. Vector's network operations centre is running service verification checks and any logical configuration or migration work needed as field work translates into restored services.