Stockland and EdgeConneX Kemps Creek data centre campus goes on exhibition
The NSW Planning Portal opened exhibition on 19 November 2026 of the environmental impact statement for Stockland and EdgeConneX's Aldington Road campus in Western Sydney, costed at about A$4.99 billion. Consumption figures vary across the planning documents, from 342MW to a 444MW maximum, and submissions close on 17 December 2026.
Public exhibition of the environmental impact statement for Stockland's Aldington Road Data Centre at Kemps Creek began on the NSW Planning Portal on 19 November 2026. IDCNOVA described the project as a 50/50 joint venture with operator EdgeConneX, with construction costed at roughly A$4.99 billion before GST. Submissions are accepted until 17 December 2026, and because the proposal is still being assessed as state significant development, exhibition does not amount to approval.
According to IDCNOVA, the EIS covers two buildings holding 33 data halls on a 30.5-hectare site in the Mamre Road industrial precinct, with a maximum IT load of 365MW. The exhibition notice lists maximum power consumption of 444MW, whereas the cost report and greenhouse assessment work from 342MW, made up of 15 halls at 12MW in Building A and 18 at 9MW in Building B. Earlier, amended requirements issued on 15 September 2026 covered up to 360MW of IT power, a measure Unite.AI says differs from the campus-wide maximum.
The campus is aimed at AI and hyperscaler customers, and its halls are designed for both air-cooled and denser liquid-cooled equipment. The EIS proposes 228 rooftop dry chillers for waterless cooling, giving a power usage effectiveness of about 1.25 that rises to an expected 1.36 once acoustic treatment is added. The assessment requirements ask for a PUE of 1.3 or below and a commitment to match operating electricity demand with NSW-based renewable supply.
Power would be drawn from Transgrid's 330kV network through a new Ropes Creek switching station that cuts into Line 14, supplying a 330/33kV substation on site. Half of the substation's 1,000MVA capacity, 500MVA, is allocated to the data centre, and the other half is held for the neighbouring 200 Aldington Road estate. Symphony Infrastructure would deliver the switching station, and the EIS says network modelling has gone to Transgrid for review.
Construction is put at 44 months from 2027, with operations expected from the first quarter of 2029 and full load by the first quarter of 2031. The cost report estimates about 1,375 full-time equivalent jobs in the build and about 84 staff once operating. Stockland anticipates a determination in 2027, an expectation rather than a fixed date.
Penrith City Council has asked for the application to be referred to the Independent Planning Commission, telling the department in September that the proposed height, then 36.4 metres, was "a significant non-compliance" with the 20-metre control. The EIS now specifies a maximum height of 31.5 metres. Once Stockland responds to submissions, the Minister for Planning and Public Spaces or the commission will decide the application.
Chief executive Tarun Gupta told shareholders at the annual meeting that the EdgeConneX partnership will "develop, own and operate an Australian portfolio of data centres." Stockland's update reports about 450MW of secured power across its platform, subject to final design and customer negotiations and not a Kemps Creek capacity. Other Sydney-area records include Wetherill Park, with about 238MW of total capacity and 170MW of IT load, and a 100MW proposal at 192 Narellan Road, Campbelltown.