Residents overwhelmingly oppose Anthropic-anchored Western Downs data centre

Nearly 600 public submissions on the proposed Western Downs Digital Park, with Anthropic as anchor tenant, were almost all opposed, according to a filing lodged for developer Zerra DC. The planned load is 1.44 gigawatts.

A proposed data centre in regional Queensland with Anthropic as its anchor tenant has drawn overwhelming opposition from residents, according to a filing for the project. Of nearly 600 public submissions on the Western Downs Digital Park, about 250 km west of Brisbane, two backed the project and one was neutral. The other 595 opposed it or asked for a delay until developers cleared certain environmental hurdles, the filing said.

The filing was lodged on behalf of developer Zerra DC, and it acknowledged that a significant number of submissions raised reasonable matters on water, power, noise, roads, housing and the scale of the project. Objectors mostly cited water use, electricity demand and prices, noise, road damage from construction traffic and pressure on housing. About one-third of the submissions came from people who lived within 200 km of the site.

The project had received five objections in a month before it named Anthropic as its tenant on 15 September, a log of public comments showed. The rest arrived between then and 11 November, when the local government stopped accepting submissions. Representatives of Zerra and Anthropic were not immediately available for comment on the filing.

The site is farmland and further from the suburbs than other proposals, but its planned computing load of 1.44 gigawatts would make it one of the country's biggest. The filing describes the first Australian facility for Anthropic, and the response, though far from binding, points to a showdown between the company and the host community. The filing was published in the same week Anthropic priced its initial public offering on Wall St, on 18 November.

Other Australian projects have met resistance. Goodman Group scrapped a data centre of roughly A$1.2 billion planned for Sydney in September after a public backlash. NextDC delayed a Melbourne project amid resident concerns about energy use, which triggered a shares selldown.