Data centres

NextDC rules out new datacentres near homes after West Footscray backlash

NextDC told its annual general meeting on Friday 20 November 2026 that it will stop pursuing sites near residential properties, after protest over power poles delayed its M3 expansion in Melbourne and shareholders delivered a second strike on executive pay.

NextDC will no longer chase new development opportunities close to homes, following community opposition to the expansion of its M3 site in West Footscray, in inner Melbourne. The Guardian reported that the backlash was followed by a 40 per cent drop in the company's share price.

The annual general meeting on Friday was the first since the M3 expansion was put back, after power provider Jemena paused construction of new 22-metre power poles amid community protest. Shareholders registered a second strike against executive pay, though a motion to spill the board was heavily defeated. The share price has climbed back above $9, but Goodman Group acquired a stake of nearly 10 per cent in NextDC in the meantime.

Chief executive Craig Scroggie described it as his "hardest AGM" in 15 years and said he ultimately carried responsibility for "delivery, power, planning, approvals, construction and community support". He said NextDC had needed to work more closely with its power and construction partners, and with the community, and was now doing so. Scroggie said residents should have been heard sooner during the Jemena works, and that ensuring this was NextDC's role. He said the company's practices had shifted, adding that "Community expectations have moved in the age of artificial intelligence and we must move with them."

NextDC said it will establish a community consultative committee that includes a standing forum for residents and local stakeholders. It also plans a dedicated project website and contact channels with defined response times for complaints and inquiries.

Flynn, speaking for NextDC, said the mood towards datacentres had changed sharply over roughly six years. He pointed out that the M3 site had been used for industry for a century, including petrochemical works before the datacentre was built. Flynn said the Jemena employee in charge of community engagement departed after the reaction to the taller poles delayed the expansion. He said Jemena had "just charging ahead regardless of community".

A Jemena spokesperson declined to comment but pointed to a September statement announcing that its general manager for electricity networks had decided to step down.