WinDC and Armada plan 3GW AI network across Australia and NZ under US export program

WinDC and Armada want to build up to 3GW of AI computing capacity at about 40 sites by the end of the decade, with the companies putting potential investment above US$30 billion under a US export scheme.

Australian modular data centre developer WinDC and its US partner Armada have set out a plan for up to 3GW of AI computing capacity spread over about 40 sites in Australia and New Zealand by the end of the decade. The pair put the total potential investment at more than US$30 billion, of which more than US$20 billion would go on Armada equipment made in the United States. Stage one is 11MW across five Australian states, and a further 230MW is slated for 2027.

The scheme sits within a US Government export effort: Armada holds Priority Team Leader status in the American SI Exports Program, and the WinDC Australian build forms part of its export plans. Business News Australia reported that the US Department of Commerce runs the program, and that participating consortia receive government advocacy, faster export licence handling at the Bureau of Industry and Security and priority access to federal financing referrals. WinDC and Armada also plan to look at financing for later stages, including through the Export-Import Bank of the United States.

WinDC would place factory-built modules at or beside wind and solar farms and other generators, avoiding metropolitan hubs where WinDC says grid limits and slow construction are a growing problem. WinDC says each Armada Leviathan unit delivers up to 2MW, and it is aiming for roughly 90 days from start to deployment where sites, power and approvals are already sorted. Armada's platform can tie several sites together into one distributed network.

The agreement between the companies cites more than seven terawatt-hours of utility-scale wind and solar output curtailed in the National Electricity Market in 2025. WinDC argues that placing modules next to generators lets it take power the grid cannot fully absorb. Chief executive Andrew Sjoquist said the project was "an opportunity to bring substantial investment into regional Australia, create economic activity around energy generation sites, and turn Australian energy into computing capacity that can be sold to customers around the world."

The companies frame the network as an export business, and WinDC points to Western Australia, whose energy resources and subsea cables it says give reach to Southeast Asia, India and the Middle East. WinDC said Southeast Asian markets of at least 500 million people lie within about 50 milliseconds of computing infrastructure on the west coast. Sjoquist said US backing "puts us at the front of the queue at a time when every nation on earth is competing for computing capacity".

Armada heads the American Sovereign SI Stack consortium with Dell Technologies and Microsoft, which pairs its modules with Dell compute and storage and Microsoft's Azure Local and Foundry Local software. Armada makes its hardware at Galleon Forge One in Gilbert, Arizona, and at the March announcement the companies said production would move to Australia once WinDC reaches a defined number of units here. WinDC commissioned its first unit with Armada in January, and the 11MW deployment, announced in March, targets wind, solar and battery sites in NSW, elsewhere in the NEM and in Western Australia.