Energy Council urges mandatory bonds for data centre grid connections
The Australian Energy Council wants the AEMC to require security from large loads and stop networks passing poorly managed connection risk to consumers, with data centre demand forecast to triple by 2030.
The Australian Energy Council (AEC) is pushing for compulsory financial security from large electricity users such as data centres, so that grid upgrade costs and risks are not left with other consumers. It made the case in a submission on two rule change requests about recovering network augmentation costs, which the Australian Government lodged and the Australian Energy Market Commission (AEMC) initiated on 24 September. The requests aim to prevent consumers unfairly carrying costs or risks created by data centre connections.
The rule changes follow the May 2026 decision on data centres by the Energy and Climate Change Ministerial Council. A separate strand of that work will oblige data centres to contract for new renewable generation and firming. The network rules are one part of a wider reform package expected to run into late 2027.
Demand growth explains the focus. AEMO's 2026 Electricity Statement of Opportunities estimates data centre electricity use could triple by 2030, from about 5 terawatt-hours now to around 15 TWh. Most of the load is expected in NSW and Victoria, with growth projected through to 2045, and serving it will need major network upgrades.
On upstream costs, the AEC sees a possible gap in the existing framework. It said a large load on a distribution network can trigger or bring forward transmission investment without paying an appropriate share. Its starting principle is that a connecting party should pay the incremental network costs that it demonstrably causes or accelerates. The council accepted this will not always be simple, since an augmentation may serve one connection, several, or wider demand growth, and said AER guidelines could help networks apply a consistent approach.
The AEC said prudential protections are optional under the current rules and therefore do not adequately protect consumers. It argued that a network expecting to recover an unsecured shortfall through its regulated asset base (RAB) may offer softer terms to win a connection. The council proposed an entry bond at application, with clear forfeiture triggers and a dispute-resolution process, to be returned when a connection agreement is executed. It also wants security to cover connection assets and upstream augmentation costs, through pre-payment or a guarantee from an investment-grade entity, applied according to load size rather than industry.
The AEC also wants networks to keep a strong incentive to manage connection risk. It suggested the AEMC consider barring RAB reallocation for customer-specific assets above a capital threshold aligned with the large-load threshold for security. Any reallocation would cover only the genuinely shared portion of an asset, and only if the AER is satisfied of material shared use, the network took all reasonable steps to recover costs from the connecting party, and the network keeps a share of the residual cost. Cost recovery for exceptional and unforeseen events could remain available after an AER assessment against defined criteria.