Data centres

IREN plans 900MW Wagga Wagga campus as council demands 1.5 per cent levy

IREN has proposed a 900MW data centre campus called Redbank on the outskirts of Wagga Wagga, a project that could draw more than $10 billion. Wagga Wagga Council has finalised a demand that the developer pay 1.5 per cent of capital costs into community funds.

Data centre developer IREN has proposed a 900MW campus on the outskirts of Wagga Wagga in southern New South Wales, a project that could attract more than $10 billion (US$7 billion) in investment. The proposal is at an early assessment stage, and IREN is working towards a grid connection starting in 2029.

According to a project website, the site lies west of the Gregadoo Waste Management Centre, on land that already hosts transmission infrastructure. Site renderings show at least four buildings of varying sizes and an on-site substation. IREN would fund transmission costs and contract new renewable energy and storage capacity to cover its power needs, and the campus would use a closed-loop cooling system designed to cut water use. IREN said the project is not part of its previously announced 5GW secured-power portfolio.

Wagga Wagga Council finalised a policy on 16 November under which IREN would be asked to pay 1.5 per cent of the project's total estimated capital costs, including components, machinery, plant and equipment, into community funds, The Nightly reported. Under the arrangement, 1 per cent would be managed directly by the council and the remaining 0.5 per cent would be jointly administered by the council and IREN. Council General Manager Peter James said the policy was developed with regard to NSW Government guidelines, local circumstances and feedback from public exhibition. He said it "establishes Council’s benchmark expectations and provides a consistent basis for negotiations with individual proponents".

IREN has not signalled that it will agree to the demand, and it did not respond to The Nightly's request for comment. The company has not confirmed Redbank's cost, though figures of up to $10 billion have previously been reported. Its online materials say the data centre could provide 200 ongoing jobs and $200 million of community support over 30 years, and The Nightly reported that it wants to build by 2029, with 500 potential construction jobs. IREN said Redbank "has the potential to create local jobs and economic stimulus as well as community benefits for the Wagga Wagga area". Final approval rests with the NSW Government.

Other developers are also active nearby: Leading Edge DC operates a small facility in the city, and CDC plans a gigawatt-scale campus in the region. IREN's management met locals twice at a Wagga Wagga pub in November to try to ease opposition to the project. The Nightly reported that IREN shares have fallen 63 per cent in 2026, with the sell-off linked to concerns about debt as it seeks funding for a pipeline across Australia and the US. Data centres account for about 3 per cent of national electricity consumption, and water use makes approvals more sensitive in drought-prone regions, according to The Nightly.